Cedar Valley Nature Trail Progress Update (May 2012)

Cedar Valley Nature Trail Paving Progress: 

Due to good weather and asphalt application in one “lift”, the paving of the Cedar Valley Nature Trail is ahead of schedule.  By the end of May, the trail will be paved from Schultz Rd. (Mile 10) to Lafayette (Mile 7). The existing metal culverts at Lafayette were removed and the installation of a new concrete culvert is underway. At Lafayette, the paving project will be 40% complete.  Even though this section is paved, trail users are reminded that the trail is still closed as workers complete periphery work.   Please respect and obey the barricades and posted signage. With the current weather conditions, the CVNT could be open before the end of summer.

CVNT Lafayette Culvert (1130 downloads ) CVNT PAVING MCNEIL RD NORTH (1226 downloads )